Postby chengyue1999 » Tue Jul 16, 2019 6:23 pm

Hi, in the result I had multiple time steps and I would like to the changing of the same profile/section. For a few steps I can do by plotting line graphs for each step, but now there are hundreds of them so it better to be done automatically. Can anybody help me out? Thanks!
User avatar
escolano
Posts: 1562
Joined: Thu Sep 18, 2014 3:31 pm

Re: Auto plot for multiple time steps

Postby escolano » Wed Jul 17, 2019 2:27 pm

I don't completely understand this question.

You can write a Tcl procedure (e.g. invoked from a macro toolbar button) that use the commands you want (GiD_Process to send keywords to be processed by GiD to do thinks, like do a cut, and Tcl commands/procs , like GiD_Graph, etc.)